Back to all announcements

DJ Lake Acquisitions Limited NPN Quarterly Disclosure

TIDMNU.P

RNS Number : 5916M

Lake Acquisitions Limited

14 October 2016

14 October 2016

Lake Acquisitions Limited

Quarterly information statement for 1 July 2016 to 30 September 2016 inclusive ("Q3 2016")

The following information is provided by Lake Acquisitions Limited as issuer of the CVRs to which the Nuclear Power Notes are linked, in satisfaction of its disclosure obligations under the Conditions of the CVRs, but is not directly relevant to the calculation of any payment due under the CVRs or the Nuclear Power Notes, for the reasons described below.

 
 1. Month Ahead Prices 
  Month Ahead Prices in respect 
  of Q3 2016 
   *    July 2016                                                   : 35.94 GBP/MWh(1) 
                                                                    : 37.52 GBP/MWh(1) 
                                                                    : 37.62 GBP/MWh(1) 
   *    August 2016 
 
 
   *    September 2016 
 2. Contribution to Eligible Nuclear 
  Output                                                             : 17.1 TWh(2) 
  Contribution to Eligible Nuclear 
  Output in respect of Q3 2016 
 Cumulative Contribution to Eligible                               : 48.0 TWh(2) 
  Nuclear Output in respect of the 
  calendar year 2016 (1 January 
  2016 to 30 September 2016 inclusive) 
 3. Likely maximum theoretical 
  output before unplanned losses                                     : 17.4 TWh(3) 
  Likely maximum theoretical output 
  before unplanned losses for the 
  EDF Energy Nuclear Generation 
  Fleet in respect of the period 
  from 1 October 2016 to 31 December 
  2016 inclusive 
      4. Total quantum of planned power 
       outages(4)                                                    : 4.5 TWh(3) 
       Total quantum of planned power 
       outages for the EDF Energy Nuclear 
       Generation Fleet in respect of 
       the period from 1 October 2016 
       to 31 December 2016 inclusive 
       The total comprises: 
        *    Planned power outages of approximately 2.7 TWh(3) 
             attributable to restrictions, statutory outages and 
             refuelling 
 
 
        *    Planned power outages of approximately 1.1 TWh(3) 
             attributable to boiler restrictions at Hunterston B 
             and Hinkley Point B 
 
 
        *    Other planned power outages of approximately 0.7 
             TWh(3) including the impact of the boiler spine 
             restrictions at Hartlepool and Heysham 1 
 

Investors should note that for the purposes of calculating the Yearly Payment on the CVRs:

-- The Contribution to Eligible Nuclear Output figure disclosed in each quarterly information statement is a preliminary figure. The final figure for the Eligible Nuclear Output for the relevant year will be set out in the Payment Calculation Notice, is subject to a cap of 65 TWh in any calendar year, and may not be equal to the sum of the contribution to Eligible Nuclear Output figures disclosed in each quarterly information statement for the relevant calendar year.

-- The likely maximum theoretical output before unplanned losses for the EDF Energy Nuclear Generation Fleet in respect of the period from 1 October 2016 to 31 December 2016 inclusive is an indicative figure representing likely maximum output after taking into account known capacity of each power station in the EDF Energy Nuclear Generation Fleet and planned power outages as at the date of this announcement. The likely maximum theoretical output is therefore stated before any unplanned losses that may arise subsequent to the date of this announcement. Accordingly, this theoretical figure may be different from the actual Eligible Nuclear Output in respect of this period.

-- The total quantum of planned power outages for the EDF Energy Nuclear Generation Fleet in respect of the period from 1 October 2016 to 31 December 2016 inclusive is an indicative figure based on planned power outages known as at the date of this announcement. The total quantum of planned power outages is therefore stated before any unplanned losses that may arise subsequent to the date of this announcement. Accordingly this indicative figure may be different from the total quantum of actual planned power outages in respect of this period.

For further details, including in respect of the calculation of the Yearly Payment on the CVRs, please see the Terms and Conditions of the Nuclear Power Notes and the Terms and Conditions of the CVRs which are set out on pages 65 to 120 of the prospectus for the Nuclear Power Notes issued by Barclays Bank PLC on 5 November 2008 ("Prospectus"). A supplement to the Prospectus was issued by Barclays Bank PLC on 10 February 2009.

In this announcement, capitalised terms that are not defined have the meaning set out in the Prospectus.

Contacts:

 
 Media Enquiries    01452 652233 
 Davina             020 3126       (Financial Communications) 
  Ferrier            2585 
 

Notes:

   (1)   Source - ICIS Heren European Daily Electricity Markets 
   (2)   This number is rounded 
   (3)   This number is an indicative figure only and is rounded 
   (4)   Planned power outages include load restrictions 

This information is provided by RNS

The company news service from the London Stock Exchange

END

MSCUSSRRNWARAAA

(END) Dow Jones Newswires

October 14, 2016 06:51 ET (10:51 GMT)